Planned Projects

Project

Design

Construction

Furniture & Equipment

Reconfiguation – Jefferson Hall (Building J)

FY17/FY18

FY18

FY18

Renovation/Addition – Building E

FY18

FY19

FY19

Renovation – Annapolis Hall (Building A)

FY18

FY18

Renovation/Addition – Linganore Hall (Building L)

FY19

FY20

FY20

Renovation/Addition – Athletics Center (Building D)

FY21

FY22

FY23

Renovation/Replacement – Central Plant

FY18-FY22

Deferred Maintenance/Preventative Maintenance/

Life Safety Replacement

FY18-FY23