page 43
Estimated Cost Summary
Project Name
Construction Type
Construction Cost
Professional Fees,
Furniture and Equipment
Total Project Cost
(2017 dollars)
Jefferson Hall (Building J)
Reconfiguation
$1,421,000
$384,000
$1,805,000
Building E
Renovation/Addition $4,779,000
$1,057,500
$5,836,500
Annapolis Hall (Building A)
Renovation
$1,518,000
$276,000
$1,794,000
Linganore Hall (Building L)
Renovation/Addition $9,098,500
$1,217,000
$10,315,500
Athletics Center (Building D)
Renovation/Addition $10,661,000
$1,410,000
$12,071,000
Central Plant (Building D)
Replacement
$13,500,000
$0
$13,500,000
Total
$45,322,000
Project Schedule
2017
2018
2019
2020
2021
2022
Q1
Q1
Q1
Q1
Q1
Q1
Q2
Q2
Q2
Q2
Q2
Q2
Q3
Q3
Q3
Q3
Q3
Q3
Q4
Q4
Q4
Q4
Q4
Q4
Task Name
Jefferson Hall (Building J)-
Reconfiguration
Programming
Design
Construction
Building E -
Renovation/Addition
Programming
Design
Construction
Annapolis Hall (Building A) -
Renovation
Programming
Design
Construction
Linganore Hall (Building L) -
Renovation/Addition
Programming
Design
Construction
Athletics Center (Building D)
- Renovation/Addition
Programming
Design
Construction
Central Plant (Building D) -
Replacement
Construction